Constructora Vialpa, S.A.
Repair of Guaraguao Port
Marine

Repair of Guaraguao Port

1995

Project sheet

Sector
Marine
Client
Corpoven
Location
Puerto La Cruz, Anzoátegui State, Venezuela
Year
1995
Investment
Bs. 300,000,000 / US$ 2,000,000
Vialpa Role
Port repair and reconstruction

Project overview

Repair of Guaraguao Port. Works included prefabrication of concrete beams and slabs; partial and complete demolition of damaged beams and slabs; reconstruction of salvageable beams; driving of 66 steel piles of 24-inch diameter and 3/8-inch thickness; installation of new prefabricated beams and slabs; and on-site pouring of topping. The project required constructing a temporary 150-meter steel dock to carry out the repair while ensuring no interference with dock unloading operations. Contract duration: 10 months.

The Challenge

Repair an operational dock, requiring the construction of a 150-meter temporary steel dock to carry out repairs without interrupting Corpoven's unloading operations.

Vialpa Scope

Prefabrication of concrete beams and slabs; partial and complete demolition of damaged beams and slabs; reconstruction of salvageable beams; driving of 66 steel piles of 24 inches; installation of new prefabricated beams and slabs; on-site pouring of topping; and construction of a 150-meter temporary steel dock.

Engineering / Construction Approach

Construction of a 150-meter temporary steel dock to isolate repair works from the wharf's active unloading operations, combining prefabricated elements to optimize structural assembly over water.

Operational Constraints

No interference with dock unloading operations during execution. Construction of a 150-meter temporary steel dock for repairs. Complete the works within a 10-month timeframe.

Technical Highlights

  • Driving of 66 steel piles of 24-inch diameter and 3/8-inch thickness
  • Construction of a 150-meter temporary steel dock for repairs
  • Prefabrication of concrete beams and slabs and reconstruction of salvageable beams
  • Executed without interfering with dock unloading operations

Key Quantities

66 (24", 3/8")
Steel piles
150 m
Temporary dock
10 months
Contract duration
Corpoven
Client
1995
Year
Project Gallery

Photographic archive and field execution

Original photographic field documentation of road execution, structures, concrete barriers and earthmoving by Constructora Vialpa.

Aerial panoramic view of Guaraguao Port and Terminal facilities showing berthed oil tankers, piers and industrial yard
Field Archive

Aerial panoramic view of Guaraguao Port and Terminal facilities showing berthed oil tankers, piers and industrial yard

Structural dock repair works on piles featuring lattice crawler cranes, heavy equipment and superstructure steel assembly over water
Field Archive

Structural dock repair works on piles featuring lattice crawler cranes, heavy equipment and superstructure steel assembly over water

Controlled technical demolition using pneumatic jackhammer on the concrete dock slab for structural rehabilitation
Field Archive

Controlled technical demolition using pneumatic jackhammer on the concrete dock slab for structural rehabilitation

Let's discuss your next project.