Plastic Processing Industrial Complex — Injection Modules M6, M7, M8, M9 and M10
Project sheet
- Sector
- Industrial
- Client
- Ministerio del Poder Popular para Ciencia, Tecnología e Industrias Intermedias — Corpivensa
- Location
- San Francisco de Yare, Simón Bolívar Municipality, Miranda State, Venezuela
- Year
- 2011
- Investment
- BsF. 275,000,000 (Oct 2011) + BsF. 39,194,341 (complementary contract)
- Vialpa Role
- Construction of industrial modules and complementary civil works
Project overview
Construction of modules for the socialist plastic-processing factory promoted by the Ministry of People's Power for Science, Technology and Intermediate Industries with its affiliate Corpivensa, divided into two locations (Ocumare and Yare). As part of the first phase, five modules with thirteen injection machines each are planned, for a total of 65 injection machines, plus a molds-and-dies module for maintenance and mold manufacturing. Additional contracted works include preliminary works, installation, voice and data, culverts, foundation, grounding system, internal roads, earthworks, concrete works, formwork, steelworks, asphalt, signage, a multipurpose sports court, sports equipment, enclosures, electrical installations, landscaping, external furniture and complementary works.
The Challenge
Build five industrial modules simultaneously with their civil and complementary installation works, coordinating civil, electromechanical and services works to enable an operational plastic-processing plant.
Vialpa Scope
Construction of five injection modules (M6, M7, M8, M9 and M10) with 13 machines each, molds-and-dies module, and complementary works: preliminary, installation, voice and data, culverts, foundation, grounding, internal roads, earthworks, concrete, formwork, steel, asphalt, signage, sports court, equipment, enclosures, electrical, landscaping and furniture.
Engineering / Construction Approach
Phased execution coordinating the supporting civil works with the installation of the injection lines and service systems, ensuring the progressive commissioning of each industrial module.
Technical Highlights
- 5 modules with 13 injection machines each (65 machines total)
- Molds-and-dies module for maintenance and mold manufacturing
- Comprehensive civil works: earthworks, concrete, formwork, steel, asphalt and electrical
- Contract signed September 6, 2011 with Corpivensa
Key Quantities
Photographic archive and field execution
Original photographic field documentation of road execution, structures, concrete barriers and earthmoving by Constructora Vialpa.

Completed industrial injection hall with operational line of injection machines, workstations and high-strength polished concrete flooring

Battery of high-precision plastic injection molding machines installed in the production module with pneumatic and electrical connections

Specialized molds-and-dies module equipped with 5-ton overhead crane, lathes, CNC milling machines and machining centers for mold maintenance

Assembly of reticulated structural steel frame, runway beams for overhead crane, siding panels and service raceways in industrial hall

Structural steel erection phase of main frames and trusses over reinforced concrete foundations and slab