Internal Access Roads and Terraces – Río Cuira Dam Works (Project Tuy IV)
Roadway

Internal Access Roads and Terraces – Río Cuira Dam Works (Project Tuy IV)

2011

Project sheet

Sector
Roadway
Client
HIDROCAPITAL / Ministerio del Ambiente (en asociación con Camargo Correa, S.A.)
Location
Miranda State, Venezuela
Year
2011
Investment
69,559,000 Bs (as of May 2011)
Vialpa Role
Construction and maintenance of internal access roads and site terraces

Project overview

In partnership with the Brazilian construction group Camargo Correa, S.A., Vialpa worked with HIDROCAPITAL as executing entity for the Ministry of the Environment on the construction and maintenance of internal access roads and site terraces for the temporary facilities of the Cuira River Dam, as part of the Tuy IV project. The work includes the expansion and construction of a treatment plant and several social-impact projects in the area of influence, all with national engineering, over an approximate execution period of six months.

The Challenge

Build and maintain the internal access infrastructure and site terraces for the temporary facilities of a major dam, coordinating execution under an international partnership structure with Camargo Correa, S.A., within an approximate six-month timeframe.

Vialpa Scope

Construction and maintenance of internal access roads and site terraces for temporary facilities, expansion and construction of a treatment plant, and social-impact projects in the area of influence of the Cuira River Dam (Project Tuy IV).

Engineering / Construction Approach

Execution in partnership with Camargo Correa, S.A., combining Vialpa's local experience in roadway and earthworks infrastructure with the capacity of an international construction group, under the coordination of HIDROCAPITAL as executing entity for the Ministry of the Environment.

Operational Constraints

Work contracted in May 2011 for 69,559,000 bolívares, with an approximate execution period of six months and national engineering.

Technical Highlights

  • Partnership with Brazilian construction group Camargo Correa, S.A.
  • Internal access roads and site terraces for temporary facilities of the Cuira River Dam
  • Expansion and construction of a treatment plant and social-impact projects
  • National engineering, approximate execution period of six months

Key Quantities

HIDROCAPITAL / Ministerio del Ambiente
Client
Camargo Correa, S.A.
Partner
Roadway / Earthworks / Hydraulics
Sector
Mayo 2011
Contract
69.559.000 Bs
Investment
~6 meses
Execution period
Project Gallery

Photographic archive and field execution

Original photographic field documentation of road execution, structures, concrete barriers and earthmoving by Constructora Vialpa.

Pioneering and shaping of the internal access road across mountainous jungle terrain with heavy machinery and dump trucks (September 2011)
Field Archive

Pioneering and shaping of the internal access road across mountainous jungle terrain with heavy machinery and dump trucks (September 2011)

Hillside cuts, benching and site terrace grading with crawler excavator loading an all-terrain articulated dump truck
Field Archive

Hillside cuts, benching and site terrace grading with crawler excavator loading an all-terrain articulated dump truck

Completed roadway section with rigid concrete slab pavement and slope stabilization along the access corridor
Field Archive

Completed roadway section with rigid concrete slab pavement and slope stabilization along the access corridor

Related capabilities

Let's discuss your next project.