Constructora Vialpa, S.A.
“Virgen de Coromoto” Water Treatment Plant
Water

“Virgen de Coromoto” Water Treatment Plant

2001

Project sheet

Sector
Water
Location
Guanare, Portuguesa State, Venezuela
Year
2001
Vialpa Role
Water treatment plant construction and electromechanical works

Project overview

The “Virgen de Coromoto” Water Treatment Plant has the capacity to treat 1,500 liters per second of raw water. It features an aeration cascade that reduces organic matter and oxidizes reducing compounds such as iron and magnesium ions; four pulsating sludge-bed settlers (super pulsators); and five ABW filters with a self-cleaning cell design that saves water, air and energy. It also includes chlorine storage and dosing facilities, pumps and compressors, an emergency power generation plant, and administrative areas housing the Water Quality Control Laboratory. Its commissioning guarantees the water supply for Guanare and surrounding areas until the year 2050.

The Challenge

Build a treatment plant capable of processing 1,500 L/s of raw water using pulsating sedimentation and self-cleaning filtration technology, ensuring a sustainable supply for Guanare and surrounding areas until the year 2050.

Vialpa Scope

Construction of the complete treatment plant: aeration cascade, four pulsating sludge-bed settlers (super pulsators), five self-cleaning ABW filters, chlorine storage and dosing facilities, pumps and compressors, emergency power generation plant, administrative areas and the Water Quality Control Laboratory.

Engineering / Construction Approach

Integration of advanced treatment processes —aeration, pulsating sedimentation and ABW self-cleaning filtration— with coordinated civil and electromechanical works to optimize water, air and energy consumption, and ensure treated-water quality through the Quality Control Laboratory.

Operational Constraints

The plant had to guarantee drinking-water supply for Guanare and surrounding areas with a projection to the year 2050, requiring long-term operational reliability and redundancy through the emergency power generation plant.

Technical Highlights

  • Treatment capacity of 1,500 L/s of raw water
  • Four pulsating sludge-bed settlers (super pulsators)
  • Five ABW filters with self-cleaning cell design
  • Water supply guaranteed for Guanare until the year 2050

Key Quantities

1.500 L/s
Treatment capacity
4 super pulsators
Settlers
5 ABW (self-cleaning)
Filters
2050
Supply guaranteed until
Water / Electromechanical
Sector
Project Gallery

Photographic archive and field execution

Original photographic field documentation of road execution, structures, concrete barriers and earthmoving by Constructora Vialpa.

Aerial panoramic view of the “Virgen de Coromoto” Water Treatment Plant with 1,500 L/s capacity, sedimentation modules, filters and illumination towers
Field Archive

Aerial panoramic view of the “Virgen de Coromoto” Water Treatment Plant with 1,500 L/s capacity, sedimentation modules, filters and illumination towers

Battery of pulsating sludge-bed settlers (super pulsators) with clarified water collection channels and inspection catwalks
Field Archive

Battery of pulsating sludge-bed settlers (super pulsators) with clarified water collection channels and inspection catwalks

Electromechanical rapid mixing and agitation assembly with vertical geared motor mounted on central grating walkway with safety railings
Field Archive

Electromechanical rapid mixing and agitation assembly with vertical geared motor mounted on central grating walkway with safety railings

Traveling wash bridge and suction mechanism for ABW self-cleaning cell filters with control panel and serrated overflow weirs
Field Archive

Traveling wash bridge and suction mechanism for ABW self-cleaning cell filters with control panel and serrated overflow weirs

Let's discuss your next project.